Boulter Installs Two Transformers for 6.4 MW Solar Farm in Geneseo, New York

In the dynamic landscape of renewable energy, the success of solar projects hinges not only on cutting-edge technology but also on the collaborative efforts of experienced, efficient local partners. GreenSpark Solar, a notable player in the solar energy sector, has consistently embraced this philosophy in their mission to promote sustainable power generation. Discover why GreenSpark strategically selected Boulter to play a pivotal role in their latest endeavor – a 6.4 MW solar project owned by Catalyze.

Customer Request

The solar energy sector has seen remarkable growth, with GreenSpark Solar at the forefront of the movement in New York State. With a track record spanning over two decades, they have consistently delivered cost-effective, locally-sourced clean energy solutions. This wealth of experience and commitment to sustainability positions them as a true leader in the field.

In their latest venture, a 6.4 MW solar project owned by Catalyze, GreenSpark Solar encountered the need for specialized support for the installation of two transformers onsite. Recognizing the importance of safety and reliability for this task, they turned to Boulter, a trusted industrial partner, to ensure the project's success.

Solution

As the solar farm was being built, Boulter helped the GreenSpark team by providing a secure warehouse for the transformers until they could be installed.  After that, we loaded the transformers onto our open landoll trailer and transported them to the project site. Each transformer was lifted into place by crane and set in place safely. The GreenSpark team was happy with our bundled services because they helped them avoid project delays and additional costs and we were proud to contribute to a project that supports a greener future.

Project Highlights

  • Received and stored the transformers at our facility, eliminating the need for multiple vendors and saving the customer money
  • Transported the units to the solar farm using a flatbed trailer
  • Carefully set the units in place using a 50-ton crane

Capabilities Applied

  • Rigging
  • Warehouse and Storage
  • Trucking

Equipment

  • Rigging gang box
  • Blocks
  • Open landoll trailer
  • 50-ton crane